/ DPS High Schools
 |
|
Detroit, MI / 750,000 sf / $140 million – combined for 5 schools |
 |
Demand a Higher Standard℠
Five high schools were involved in design phase commissioning for the Detroit Public Schools bond program. HEA also performed construction phase commissioning at two of the five, Cass and Central High Schools. The scope included the mechanical, electrical, plumbing, life safety, and control systems in these new and renovated schools consisting of office space, classrooms, gymnasium, cafeteria, kitchen, media center, and mechanical rooms.
The purpose of commissioning was to inspect each system and component during construction and then functionally test thereafter to ensure that the equipment operated as intended. All deficient items found during the commissioning process were documented and corrected to optimize building efficiency and improve the comfort of the occupants.