  Detroit, MI / 630,000 sf / $80 million – combined for 14 schools
Demand a Higher Standard
Fourteen schools were involved in this Detroit Public Schools project. HEA provided commissioning and consulting services to the DPSPMT for the new construction of six early learning centers that serve students from Pre-K to 8th grade, and retro-commissioning and new construction commissioning at eight elementary schools within the district.

Functional performance testing forms and documents were developed for equipment within the mechanical, electrical, fire alarm, and kitchen systems and on-site field engineering support was provided to oversee and coordinate the functional testing. HEA helped ensure that the underfloor air distribution system was installed and working properly saving approximately $52,000 per year or $0.19 per sf in utility costs.