Project Showcase

Blog Post List

National Hospital Week, Project Spotlight: University of Rochester, Golisano Children's Hospital 

May, 08, 2019 at 13:00

Back in 2012, Horizon Engineering Associates, LLP (HEA) was contracted to provide commissioning services for the Golisano Children’s Hospital project, the largest capital project in the University of Rochester’s history. The new 8-story tower has approximately 245,000 sf and contains a two-story atrium, imaging suites, conference centers, operating rooms, neonatal intensive care unit, private patient rooms, resource library and playrooms.

Now completed, HEA provided LEED commissioning services to satisfy the LEED Energy and Atmosphere Prerequisite 1: Fundamental Commissioning of the Building Energy Systems and Credit 3: Enhanced Commissioning for the project. Systems commissioned included plumbing, BMS/controls, lighting controls, fan coil units, VAV boxes, electric heaters, AHUs, exhaust fans, snow melt and chilled water pumps.

Client: University of Rochester  

SF: 245,000 sf

Q/A with Scott Lance, Engineering Manager

Based off of client feedback, where do you feel HEA’s services provided the most value to this project?

HEA provided the most value on this project by having a Commissioning Team that was able to navigate through Siemens Apogee and Desigo User Interfaces. By utilizing former Siemens Employees HEA was able to determine issues down to the actual line of programming with out the assistance of the controls vendor. This helped to gain days on a tight project schedule since HEA and Siemens could work independently from each other. Typically on commissioning projects the controls vendor would have to assist the CxA during testing, since this now was not required the CxA could test out system and any operational issues or enhancements required could then be worked on by the controls vendor in a faster fashion then typical.

...
 

Project Spotlight: New York-Presbyterian Hospital, Allen Hospital Boiler CSS Project 

May, 02, 2019 at 15:00

HEA was contracted by the New York-Presbyterian Hospital to perform commissioning services for the Allen Hospital Central Sterilization project. The project was a facility upgrade and renovation that was originally conceived to accommodate the growing requirements for sterilization services and included an MEP upgrade of the existing central sterilization facility to accommodate for new equipment. The upgrades also included the installation of a pre-fabricated high pressure steam boiler plant that provided steam to the new facility in such a manner that allowed for redundancy and did not require a high pressure steam supply or a consistent high pressure operator presence.

HEA was responsible for the commissioning of the facility’s following systems: ductwork, roof top packaged AC unit, VAVs, exhaust fans, electric unit heaters, steam piping, steam boilers, semi-instantaneous hot water heaters, humidifier, building automation, electrical panels, transformers, heat trace, feed water pumps, AC compressor and RO filtration. HEA’s commissioning process included all work required to satisfy the LEED project requirements for EA Prerequisite 1, Fundamental Building Systems Commissioning and EA Credit 3, Enhanced Commissioning.

Client: New York-Presbyterian Hospital

Location: New York, NY

Q/A with Mykhaylo Hroshko

When first contracted for this project, what did the client express as the main goal / most pressing need for our services to accomplish?

The main goal for this new rooftop boiler plant was to have it provide enough stream pressure to the central sterilization plant located in the basement without having to operate a high pressure boiler; which would require a staffed boiler watch. The incorporated boiler plant combined four (4) low pressure boilers (1/4 is for standby/switchover purposes) that supply steam through one manifold to the sterilization plant. The most pressing need for our services to accomplish was to ensure that all boilers were operating as designed as well as to properly train the staff on how to maintain, operate and switchover boilers.

...
 

Project Spotlight: Thaddeus Stevens Technology Manufacturing Center 

April, 09, 2019 at 04:00

Horizon Engineering Associates, LLP (HEA) was contracted by the Pennsylvania Department of General Services to provide construction stage commissioning services for the Thaddeus Stevens College of Technology Manufacturing center project. HEA’s scope of work included pipe/duct testing and commissioning of the following systems: ventilation, cooling, heating hot water, and plumbing, building automation, electrical, fire alarm and fire protection.

Client: Pennsylvania Department of General Services  

Location: Lancaster, PA

SF: 44,000 sf

Q/A with Kyle Shepherd, Field Engineer II

When first contracted for this project, what did the client express as the main goal / most pressing need for our services to accomplish?

I was brought on to this job to help the Baltimore office from NYC in the middle of the construction phase of this project. When I arrived, the most pressing need from our client, PADGS, was to have the new facility fully commissioned and ready to go as soon as possible. Our main goal was to ensure this new educational center’s MEP systems were operating properly, and as energy-efficient as possible.

...
 

Project Spotlight: Manhattan Supreme Court, Energy Conservation Measures (ECM) Implementation 

March, 12, 2019 at 32:00

The New York City Department of Design and Construction (NYCDDC) contracted HEA to provide existing building commissioning services for the Manhattan Supreme Court ECM Implementation project in New York, NY. Services being provided include the commissioning of the following systems: electrical, demand control ventilation, chillers, condenser water pumps, cooling tower, and HVAC sensors and controls.

Client: New York City Department of Design and Construction (NYCDDC)  

SF: 322,000 sf

Location: New York, NY

Q/A with JT Himelrick, Field Engineer

When first contracted for this project, what did the client express as the main goal/most pressing need for our services to accomplish?

Since my involvement in this project, the most pressing need for HEA has been in the air handling unit controls upgrade. Since each unit has numerous sensors and equipment that are being upgraded, keeping track of the issues that arose and their solutions has proven to be a challenge and the service most needed from HEA.

...
 

Project Spotlight: Hudson Valley Hospital MRI Replacement 

February, 26, 2019 at 04:00

Horizon Engineering Associates, LLP (HEA) was contracted by Group PMX, LLC to provide design phase commissioning services for the Hudson Valley Hospital MRI Replacement project in Cortlandt Manor, New York. HEA’s scope of work includes commissioning of the mechanical, electrical and plumbing systems to ensure all that all systems and equipment are installed and operating according to design intent.

Client: Group PMX, LLC  

Location: Cortlandt Manor, NY

Q/A with Anthony Grgas, Senior Project Engineer

Have you ever commissioned a project involving an MRI replacement before? If so, what are the challenges with these types of projects that you have faced before and if not, what challenges are you expecting to possibly come across?

I have commissioned an MRI project before and there are many interesting aspects and challenges about them:

  • All building materials within the MRI room must be ferromagnetic (for example-only aluminum lighting fixtures and stainless steel duct)
  • The entire MRI is encased in a shell constructed out of copper sheets/plates to act as a faraday cage and block out radio noise that could interfere with the imaging process
  • The supermagnet within an MRI magnet is usually filled with helium at cryogenic temperatures, that must be provided with a cryogenic venting system as an instantaneous means of venting (in case anything goes wrong with the magnet or magnet cooling system)
  • The cooling is usually provided by a dedicated process chiller, with an emergency domestic water switchover for emergency cooling in case of chiller (or chilled water pump) failure
  • All mechanical equipment must be on critical emergency power circuits
...
 

Project Spotlight: All Aboard Florida, Miami Central Station 

February, 12, 2019 at 35:00

   
Skidmore, Owings & Merrill, LLP hired HEA to provide building envelope consulting services for the Miami Central Station (a part of the 235-mile network of rail lines that will connect South Florida to Central Florida). This massive elevated station will sit on various blocks of parking lots between the Metrorail tracks and NW 1st Avenue, connecting to the Government Center station. This facility will serve as a place where trains, buses and shuttles will all meet under one gigantic roof. HEA is providing ongoing building enclosure consulting and peer review services for the exterior enclosure systems, which includes duties such as: Review of curtain wall, metal panels and extruded aluminum infill screen; review of soffit system design and shop drawings; review of any glazing impact testing; review of visual mock-up drawings and specimens including standalone glass sample reviews, factory inspections; site visits and attendance at project meetings as required in New York City and Florida.

Client: Skidmore, Owings & Merrill, LLP

SF: 180,000 sf

Location: Miami, FL

...
 

Project Spotlight: George Washington Bridge Bus Station, New York, NY by Frank DiSalvo 

January, 30, 2019 at 18:00

The George Washington Bridge Bus Station (GWBBS) is located in Upper Manhattan and averages more than 20,000 customers per day. This project was an adaptive re-use of the existing GWBBS facility and has a life expectancy of 50 years. The project included consolidated bus operations, direct vertical transportation from the street and subway levels and 120,000 sf of retail space. HEA’s scope of work included all mechanical, electrical and plumbing systems; all of which met the necessary requirements to satisfy the Port Authority of New York and New Jersey Sustainable Design Guidelines for Energy Environmental Qualities Credits (EEQ)-2 Building Systems Commissioning.

Q/A with Frank DiSalvo, Senior Project Engineer

When first contracted for this project, what did the client express as the main goal / most pressing need for our services to accomplish?
HEA’s initial commissioning discussions with STV, Inc. began with a minimal outline of coverage, beginning only with the interests of covering the basic major systems of this bus station overhaul back in the early period of March 2010. The progress and relationship began slowly with a need for improvement on the work progress and coordination of system testing.

What was the biggest challenge faced during this project and how was HEA able to navigate through any problems faced due to this challenge?
The project was experiencing unforeseen delays and sluggish progress partway into construction, so one of the many challenges faced was managing onsite commissioning with uncoordinated contractors and project managers. With high scheduling and budget concerns, HEA teamed up with a new project director (DV) and began conducting regular progress and commissioning meetings to get all contractors and subs onboard towards a team goal.

...
 

Project Spotlight: 350 Park Avenue, New York, NY by Dan Chavez 

January, 16, 2019 at 02:00

HEA was hired by Citadel LLC to provide commissioning services for 350 Park Avenue, a commercial high-rise building in New York, NY. HEA’s scope of work included all mechanical, electrical and fire protection systems including chilled water pumps, VRFs, CRAC units, VAVs, exhaust fans and electrical panels and all emergency power systems including automatic transfer switches, uninterrupted power systems, static transfer switches and the emergency generator. HEA also worked with installing contractors to develop start-up plans and provide guidelines for several pre-functional requirements including point to point testing, flushing & cleaning piping systems, testing adjust & balancing (TAB), pre-testing of sequence of operations and verification of base building provided systems.

...
 

Spot the Deficiency! January 2019 

January, 03, 2019 at 18:00

Q: What needs to be fixed?

A: This is a deficiency because the duct is going to run into the pipe. Either the pipe or the duct has to be moved. If this was not caught by the commissioning process, the project would not be able to continue; the ductwork could not be finished until the pipe moved.

Did you get it right? Let us know!

Thank you to Phil McCrory, QCxP, Field Engineer, for capturing this.

...
 

Spot the Deficiency! December 2018 

December, 12, 2018 at 48:00

Q: What needs to be fixed?

A: Questionable temporary shoring used to support an unstable shelf angle at a brick veneer parapet.

Did you get it right? Let us know!

Thank you to Eric Turcotte, Field Engineer, for catching this.

...